RAPID Project
RAPID Project

Refinery & Petrochemical Integrated Development (RAPID) Project

Owner: PRPC Refinery and Cracker Sdn. Bhd
Client: Toyo Engineering & Construction Sdn. Bhd.
Package: Cracking Heater & Piping Erection Work
Project Location: RAPID Steam Cracker Complex, Pengerang
Original Project Schedule: March 2016 to November 2018
Additional Work Schedule: January 2019 to December 2020
(Including Pre-commissioning, Commissioning, and Plant start-up assistance)
Peak Manpower: 1200
 
Project Value: RM 365,000,000
 
 
 
Main Scope of Work Work Volume
Pipe Rack Structure Installation 2,224 Ton
Cracking Heater Installation 12,693 Ton
Field Piping Erection
Piping Around Heater & Pipe Rack Piping
94,862 dia-inches
Vendor Heater Piping
25,420 dia-inches
Refractory Work 2, 034 Ton